Stage 1. March to May 2025
The terraces and the fire
Two terraces held by dry stacked limestone, the steps between them, and the fire pit on the lower one. The upper terrace was left as packed gravel, ready for a roof.
See Brentwood's rules for a wall on a slope- On site
- 8 weeks
- Band on the drawing
- $96,000 to $112,000
- Last invoice
- $104,800